Construction Management

WBS, schedule progress and earned-value metrics for the active build.

Planned %
57.9%
Baseline to date
Actual %
53.8%
Reported physical
SPI
0.93
Schedule slip
CPI
1.00
Under budget
Work Breakdown Structure
Weighted progress with status flags.
WBSPackageWt %PlanActualStatus
1.0Project mobilisation5100%
100%
Complete
2.0Civil & structural2290%
86%
In progress
2.1 — Earthworks & foundations8100%
100%
Complete
2.2 — Building envelope1480%
72%
At risk
3.0Mechanical (cooling)2055%
48%
In progress
4.0Electrical (MV/LV/UPS)2450%
52%
In progress
5.0Fire & life safety830%
20%
In progress
6.0IT fit-out & cabling1210%
0%
Not started
7.0Commissioning Lx90%
0%
Not started
Earned-value trend (USD M)
BCWS vs ACWP vs BCWP across reporting months.
Monthly progress (planned vs actual %)